2020 Street Improvement Updates

May 14, 2021

Construction has begun on this year’s street improvement project. The contractor has split the project into smaller areas for coordination and scheduling:
  1. Area 1: The Shenandoah neighborhood located east of I-694 and north of 50th Street. View area 1 map.
  2. Area 2: The commercial industrial areas east and west of I-694, north of 4th Street and south of 10th Street. View area 2 map.
  3. Area 3: The Oakdale Park trail from Hadley Avenue to the Discovery Center and west to Granada Avenue. View area 3 map.
The improvements include miscellaneous storm sewer/sanitary sewer/water main repairs and replacement, replacement of isolated sections of structurally damaged curb and gutter, repaving of the asphalt pavement section, installation of new street lighting, and some trail and walk improvements.

MN Paving is the contractor for this project. They have successfully completed many similar projects for the City. All project work is scheduled to be complete by early September.

Current and Planned Work


Area 1

Shenandoah Valley neighborhood located east of I-694 and north of 50th Street

  • The pipe contractor is beginning work to repair existing storm sewer structures and malfunctioning watermain valves, which will take about a week to complete.
  • Isolated areas of damaged concrete curb and gutter are being removed for replacement. The concrete contractor plans to begin replacement next week, with new concrete scheduled for the end of the week.
  • The lighting contractor plans to begin installation of new wiring in about a week if materials are available. This work will take about two weeks to complete.

Area 2 

Commercial-industrial area east of I-694, north of 4th Street and south of 10th Street

  • Work is planned to start here next week (May 17) east of I-694 with some fire hydrant and storm sewer pipe work.
  • Work is planned to start May 27 west of I-694.

Area 3

Oakdale Park trail from Hadley Avenue to the Discovery Center and west to Granada Avenue

  • Work is planned to start here in early August.
As construction progresses, please use caution traveling within the project area. Also, please do not park vehicles on the street from 7 am to 7 pm within the project area unless instructed to by the contractor to accommodate driveway work. This will help the contractor to work more efficiently, and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation.

If there are any questions or comments regarding the project, please contact one of the following people:
  • Joe Meemken, 651-724-5588, On Site Project Representative, SEH
  • Brian Bachmeier, 651-730-2730, Oakdale Public Works Director/City Engineer
  • Todd Blank, 651-490-2017, Project Manager, SEH
Share on Facebook
Share on Twitter
Share via Email

Copyright 2020. City of Oakdale. All Rights Reserved.
1584 Hadley Avenue N., Oakdale, MN 55128

Powered by
CivicSend - A product of CivicPlus