2020 Street Improvement Updates

July 7, 2022

Construction has begun on this year’s street improvement project. The contractor has split the project into smaller areas for coordination and scheduling (see project area Map on City website www.ci.oakdale.mn.us):
  1. 31st Avenue neighborhood west of Ideal Avenue and north of Stillwater Boulevard (Anna's Grove).
  2. 4th Street between Helmo Avenue and Inwood Avenue.
  3. Imperial Avenue/Oak Marsh Drive/3rd Street from 4th Street to Inwood Avenue.
The improvements include miscellaneous storm sewer/sanitary sewer/water main repairs and replacement, replacement of isolated sections of structurally damaged curb and gutter, repaving of the asphalt pavement section, installation of new street lighting, and some trail and walk improvements. On 4th Street the rural roadway with ditches will be replaced with an urban roadway with curb and storm sewer.
 
Miller Excavating is the Contractor for this project. They have successfully completed many similar projects locally. All project work is scheduled to be complete by September.
 
Current and Planned Work

Area 1: 31st Avenue Neighborhood west of Ideal Avenue and north of Stillwater Boulevard (Anna's Grove)
  • The first layer of asphalt is now complete.
  • Driveways are being patched in now.
  • Irrigation repairs are planned to start on Saturday.
  • Topsoil placement in the disturbed boulevard areas is planned for next week.
  • Adjusting manhole castings and water valve boxes to their final elevation is also planned for next week.
Area 2: 4th Street between Helmo Avenue and Inwood Avenue
  • Work is planned to start here on Monday July 11.  A detour around the project area using Inwood Avenue/10th Street/Helmo Avenue will be set up. 
  • Access to Guardian Angels Church will be off of 3rd Street during this work.  Access to Oak Meadows Senior Living and to Holly Lane will be available off of 4th Street.
  • The pavement is planned to be reclaimed into gravel late next week.
Area 3: Imperial Avenue/Oak Marsh Drive/3rd Street from 4th Street to Inwood Avenue
  • Work is planned to start here on Monday July 11 with damaged curb and gutter replacement and storm sewer repairs.
  • Imperial Avenue/Oak Marsh Drive pavement is planned to be reclaimed into gravel late next week. 
  • 3rd Street will have the top surface of asphalt pavement milled off and then repaved.  This work has not yet been scheduled.
As construction progresses, please use caution traveling within the project area. Also, please do not park vehicles on the street from 7:00 a.m. to 7:00 p.m. within the project area unless instructed to by the Contractor to accommodate driveway work. This will help the Contractor to work more efficiently, and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation.
 
If there are any questions or comments regarding the project, please contact one of the following people:
 
Mike LaDoux, 651.256.0438, On Site Project Representative, SEH
Brian Bachmeier, 651.704.9970, Oakdale Consulting City Engineer
Todd Blank, 651.490.2017, Project Manager, SEH


Share on Facebook
Share on Twitter
Share via Email

Copyright 2021. City of Oakdale. All Rights Reserved.
1584 Hadley Avenue N., Oakdale, MN 55128

Powered by
CivicSend - A product of CivicPlus