Construction continues on this year’s street improvement project. The contractor has split the project into smaller areas for coordination and scheduling (see
project area map on the City of Oakdale website, www.ci.oakdale.mn.us):
- 31st Avenue neighborhood west of Ideal Avenue and north of Stillwater Boulevard (Anna's Grove).
- 4th Street between Helmo Avenue and Inwood Avenue.
- Imperial Avenue/Oak Marsh Drive/3rd Street from 4th Street to Inwood Avenue.
The improvements include miscellaneous storm sewer/sanitary sewer/watermain repairs and replacement, replacement of isolated sections of structurally damaged curb and gutter, repaving of the asphalt pavement section, installation of new street lighting, and some trail and walk improvements. On 4th Street, the rural roadway with ditches will be replaced with an urban roadway with curb and storm sewer.
Miller Excavating is the contractor for this project. They have successfully completed many similar projects locally.
Current and Planned WorkArea 1: 31st Avenue Neighborhood west of Ideal Avenue and north of Stillwater Boulevard (Anna's Grove)- Work is now complete aside from clean up items.
Area 2: 4th Street between Helmo Avenue and Inwood Avenue- Work is continuing and a detour is in place around the project area using Inwood Avenue/10th Street/Helmo Avenue.
- Access to Guardian Angels Church is from 3rd Street during this work. Access on 4th Street is only available to Oak Meadows Senior Living now from the east and to Holly Lane from the west.
- Installation of new light poles is being done now and should be complete this week.
- Sodding and seeding should be complete today.
- Traffic signage installation is being completed now.
- The final layer of asphalt paving is planned to be paved on Monday, October 10 and should take a full day to complete.
- Pavement striping is planned for later next week.
Area 3: Imperial Avenue/Oak Marsh Drive/3rd Street from 4th Street to Inwood Avenue- Work in area 3 is complete aside from street striping which will be done when 4th Street is striped.
As construction progresses, please use caution traveling within the project area. Also, please do not park vehicles on the street from 7:00 a.m. to 7:00 p.m. within the project area unless instructed to by the Contractor to accommodate driveway work. This will help the Contractor to work more efficiently, and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation.
If there are any questions or comments regarding the project, please contact one of the following people:
Mike LaDoux, 651.256.0438, On Site Project Representative, SEH
Brian Bachmeier, 651.704.9970, Oakdale Consulting City Engineer
Todd Blank, 651.490.2017, Project Manager, SEH