Project Areas
The project is broken up into different areas for coordination and scheduling. The current areas are as follows:
- Area 1: 15th Street N from Helmo Avenue N to the east City limits
- Area 2: Helmo Avenue N from Hydram Avenue N to Stillwater Boulevard
Weekly Update
- Patching in front new curb will start today (Friday, August 18) and will finish by Monday, August 21.
- Restoration is complete on Helmo Avenue, and it is currently in progress on 15th Street. The restoration of 15th Street should finish on Monday, August 21.
- Manhole and valve adjustments will start on Helmo Avenue today (Friday, August 18). The Contractor will begin on 15th Street on Monday, August 21.
- Milling of Helmo Avenue and 15th Street is planned for August 23 to 24. Paving will immediately follow August 24 to 25.
If you have any questions regarding this project, please feel free to call:
- Mike LaDoux, E.I.T, Project Representative with SEH 651-256-0438
- Jesse Farrell, P.E., City Engineer 651-730-2730
- Todd Blank, P.E., Project Manager with SEH 651-490-2017