Project Areas
The project is broken up into different areas for coordination and scheduling. The current areas are as follows:
- Area 1: 15th Street N from Helmo Avenue N to the east City limits
- Area 2: Helmo Avenue N from Hydram Avenue N to Stillwater Boulevard
Weekly Update
- All street signs will be replaced on Helmo Avenue and 15th Street next week.
- Streetlights on Helmo Avenue will be replaced in the next few weeks.
This is the final project update. Thank you for your cooperation and patience.
If you have any questions regarding this project, please feel free to call:
- Mike LaDoux, E.I.T, Project Representative with SEH 651-256-0438
- Jesse Farrell, P.E., City Engineer 651-730-2730
- Todd Blank, P.E., Project Manager with SEH 651-490-2017