Construction has begun on this year’s Street Improvement Project. The contractor has split the project into four areas for coordination and scheduling.
- Area 1: 46th Street N, 47th Street N, 48th Street N and 49th Street N (From Hadley Avenue N to the East) Area 1 Map
- Area 2: Hadley Avenue N from 40th Street N to 50th Street N Area 2 Map
- Area 3: Oakdale Nature Preserve Trail Reconstruction Area 3 Map
- Area 4: North Fire Station Parking Lot Reconstruction Area 4 Map
Improvements on Hadley Avenue N include miscellaneous storm sewer repairs, spot curb and gutter replacement, full asphalt replacement, street light replacement and bike trail reconstruction on the west side of Hadley Avenue N.
The improvements in the residential areas east of Hadley Avenue N include miscellaneous storm, sanitary and water main repairs, spot curb and gutter replacement, street light replacement and full asphalt pavement replacement.
Dresel Contracting is the contractor for this project. They have successfully completed many similar local projects. All project work is scheduled to be completed by the end of September.
Current and Planned Work
Area 1: 46th Street N, 47th Street N, 48th Street N and 49th Street N (From Hadley Avenue N to the East)
- The current light poles and bases will be removed and replaced with concrete light poles starting mid-next week.
- Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.
Area 2: Hadley Avenue N (40th Street N to 50th Street N)
- Restoration and topsoil of all disturbed areas has started. All topsoil and sod work will be completed by the end of next week.
- New light poles will be installed starting approximately mid-September.
- Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.
Area 3: Oakdale Nature Preserve Trail Reconstruction
- Tree/brush removal has started and is planned to be complete early-next week.
- Grading will begin Monday, August 12.
- The trail is tentatively scheduled to be reclaimed next week.
Area 4: North Fire Station Parking Lot Reconstruction
- Restoration and sod will be completed by the end of the week.
Reminders
As construction progresses, please use caution traveling within the project area. Also, please do not park vehicles on the street from 7 AM to 7 PM within the project area unless instructed to by the contractor to accommodate driveway work. This will help the contractor to work more efficiently and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation.
If you have any questions regarding this project, please feel free to call:
- Mike LaDoux, E.I.T, Project Representative with SEH 651-256-0438
- Brian Bachmeier, P.E., Consulting City Engineer 651-730-2730