Construction has begun on this year’s Street Improvement Project. The contractor has split the project into four areas for coordination and scheduling.
- Area 1: 46th Street N, 47th Street N, 48th Street N and 49th Street N (From Hadley Avenue N to the East) Area 1 Map
- Area 2: Hadley Avenue N from 40th Street N to 50th Street N Area 2 Map
- Area 3: Oakdale Nature Preserve Trail Reconstruction Area 3 Map
- Area 4: North Fire Station Parking Lot Reconstruction Area 4 Map
Improvements on Hadley Avenue N include miscellaneous storm sewer repairs, spot curb and gutter replacement, full asphalt replacement, street light replacement and bike trail reconstruction on the west side of Hadley Avenue N.
The improvements in the residential areas east of Hadley Avenue N include miscellaneous storm, sanitary and water main repairs, spot curb and gutter replacement, street light replacement and full asphalt pavement replacement.
Dresel Contracting is the contractor for this project. They have successfully completed many similar local projects. All project work is scheduled to be completed by the end of September.
Current and Planned Work
Area 1: 46th Street N, 47th Street N, 48th Street N and 49th Street N (From Hadley Avenue N to the East)
- Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.
Area 2: Hadley Avenue N (40th Street N to 50th Street N)
- Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.
Area 3: Oakdale Nature Preserve Trail Reconstruction
- Reclamation of the existing bike trail has started today. It will be completed by the end of the week.
- Culvert replacement will start Friday, August 16.
- Grading is starting Friday, August 16.
- Trail paving is tentatively scheduled for Wednesday, August 21 and Thursday, August 22.
- Concrete curb and pedestrian ramps are still tentative and will take place after trail paving.
- Topsoil and seeding is planned for the week of August 26.
Area 4: North Fire Station Parking Lot Reconstruction
- Work is now complete.
Reminders
As construction progresses, please use caution traveling within the project area. Also, please do not park vehicles on the street from 7 AM to 7 PM within the project area unless instructed to by the contractor to accommodate driveway work. This will help the contractor to work more efficiently and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation.
If you have any questions regarding this project, please feel free to call:
- Mike LaDoux, E.I.T, Project Representative with SEH 651-256-0438
- Brian Bachmeier, P.E., Consulting City Engineer 651-730-2730